[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125274,792,1,"单选题","关于暗挖隧道外的超前加固技术，地面锚杆正确的施作顺序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钻孔→吹净钻孔→插入锚杆→灌浆→孔口固定锚杆",false,{"key":16,"text":17,"correct":18},"B","钻孔→吹净钻孔→灌浆→插入锚杆→孔口固定锚杆",true,{"key":20,"text":21,"correct":14},"C","钻孔→吹净钻孔→插入锚杆→孔口固定锚杆→灌浆",{"key":23,"text":24,"correct":14},"D","钻孔→插入锚杆→吹净钻孔→灌浆→孔口固定锚杆","2021\u002F2020版教材P112 (2)地面锚杆（管）按矩形或梅花形布置，先钻孔→吹净钻孔→用灌浆管灌浆→垂直插人锚杆杆体→在孔口将杆体固定。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]