[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125259":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125259,792,1,"单选题","浅埋暗挖法的开挖方法中，沉降较大的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","正台阶",false,{"key":16,"text":17,"correct":14},"B","CRD工法",{"key":19,"text":20,"correct":21},"C","CD工法",true,{"key":23,"text":24,"correct":14},"D","环形开挖预留核心土法","2021\u002F2020版教材P108 表2K313031中的中隔壁法（CD工法）沉降较大。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]