[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125243":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125243,792,1,"单选题","关于隧道全断面暗挖法施工的说法，错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可减少开挖对围岩的扰动次数",false,{"key":16,"text":17,"correct":14},"B","围岩必须有足够的自稳能力",{"key":19,"text":20,"correct":14},"C","自上而下一次开挖成形并及时进行初期支护",{"key":22,"text":23,"correct":24},"D","适用于地表沉降难于控制的隧道施工",true,"2021\u002F2020版教材P105 全断面开挖法适用于土质稳定、断面较小的隧道施工，适宜人工开挖或小型机械作业。全断面开挖法采取自上而下一次开挖成形，沿着轮廓开挖，按施工方案一次进尺并及时进行初期支护。全断面开挖法优点是可以减少开挖对围岩的扰动次数，有利于围岩天然承载拱的形成，工序简便；缺点是对地质条件要求严格，围岩必须有足够的自稳能力。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]