[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125198,792,1,"单选题","下列地铁车站施工顺序中属于盖挖顺作法的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","盖挖顺做法是棚盖结构施做后开挖到基坑底，再从上至下工",false,{"key":16,"text":17,"correct":18},"B","先构筑连续墙、构筑中间支承柱，再构筑连续墙及覆盖板，开挖及支撑安装，开挖及构筑底板、构筑侧墙及顶板",true,{"key":20,"text":21,"correct":14},"C","先建临时结构顶板，根据主体结构层数，自上而下分层挖土与建造主体结构",{"key":23,"text":24,"correct":14},"D","构筑连续墙中间支承柱及临时性挡土设备，再构筑顶板，打设中间桩、临时性挡土及构筑顶板","2021\u002F2020版教材P72 盖挖顺做法是棚盖结构施做后开挖到基坑底，再从下至上施做底板、边墙，最后完成顶板 考查的是图2K313011-2盖挖顺做法施工流程 a）构筑连续墙 b) 构筑中间支撑桩 c）构筑连续墙及覆盖板 d）开挖及支撑安装 e）开挖及构筑底板 f）构筑侧墙 g) 构筑侧墙及顶板 h) 构筑内部结构及路面复旧。 D是盖挖半逆作法施工流程",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]