[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125194":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125194,792,1,"单选题","下列地铁车站施工顺序中属于明挖法的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由上向下开挖土石方至设计标高后，自基底由下向上进行结构施工",true,{"key":16,"text":17,"correct":18},"B","先建临时结构顶板，再向下开挖基坑至设计标高，由下而上建造主体结构",false,{"key":20,"text":21,"correct":18},"C","先建临时结构顶板，根据主体结构层数，自上而下分层挖土与建造主体结构",{"key":23,"text":24,"correct":18},"D","分块建筑临时结构顶板，再向下开挖基坑至设计标高，由下而上建造主体结构","2021\u002F2020版教材P70页 明挖法是指在地铁施工时挖开地面，由上向下开挖土石方至设计标高后，自基底由下向上进行结构施工，当完成地下主体结构后回填基坑及恢复地面的施工方法。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]