[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125190":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125190,792,1,"单选题","箱涵顶进设备安装的紧后工序是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","箱涵制作",false,{"key":16,"text":17,"correct":14},"B","监控量测",{"key":19,"text":20,"correct":21},"C","既有线加固",true,{"key":23,"text":24,"correct":14},"D","吃土顶进","P68-70 现场调查→工程降水→工作坑开挖→后背制作→滑板制作→铺设润滑隔离层→箱涵制作→顶进设备安装→既有线加固→箱涵试顶进→吃土顶进→监控量测→箱体就位→拆除加固设施→拆除后背及顶进设备→工作坑恢复。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]