[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125189":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125189,792,1,"单选题","拱形涵施工中，拱上端墙的正确施工顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由上至下施工",false,{"key":16,"text":17,"correct":18},"B","两侧向中间同时、对称施工",true,{"key":20,"text":21,"correct":14},"C","由下至上施工",{"key":23,"text":24,"correct":14},"D","中间向两侧同时、对称施工","P67-68 拱圈和拱上端墙应由两侧向中间同时、对称施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]