[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125185":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125185,792,1,"单选题","装配式梁，其构件应按安装的先后顺序编号存放，预应力混凝土梁的存放时间不宜超过（）个月，特殊情况下不应超过（）个月。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3、5",true,{"key":16,"text":17,"correct":18},"B","4、5",false,{"key":20,"text":21,"correct":18},"C","5、6",{"key":23,"text":24,"correct":18},"D","5、7","P62-65 构件应按其安装的先后顺序编号存放，预应力混凝土梁、板的存放时间不宜超过3个月，特殊情况下不应超过5个月。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]