[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125159":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125159,792,1,"单选题","搅拌时间是混凝土拌合时的重要控制参数，在使用机械搅拌时，它是指( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自全部骨料装入搅拌机开始搅拌起，至开始卸料时止，延续搅拌的最短时间",false,{"key":16,"text":17,"correct":14},"B","自水泥装入搅拌机开始搅拌起，至开始卸料时止，延续搅拌的最短时间",{"key":19,"text":20,"correct":14},"C","自全部胶结料装入搅拌机开始搅拌起，至开始卸料时止，延续搅拌的最短时间",{"key":22,"text":23,"correct":24},"D","自全部材料装入搅拌机开始搅拌起，至开始卸料时止，延续搅拌的最短时间",true,"P39-41 搅拌时间是混凝土拌合时的重要控制参数，使用机械搅拌时，自全部材料装入搅拌机开始搅拌起，至开始卸料时止，延续搅拌的最短时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]