[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125146":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125146,792,1,"单选题","测量工作对箱涵顶进很重要，必须( )，做好记录并报告现场指挥。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","每一顶程测量一次各观测点高程偏差值",false,{"key":16,"text":17,"correct":14},"B","每一顶程测量一次各观测点左、右偏差值",{"key":19,"text":20,"correct":14},"C","每一顶程测量一次各观测点高程偏差值和左、右偏差值",{"key":22,"text":23,"correct":24},"D","每一顶程测量一次各观测点高程偏差值，左、右偏差值和顶程及总进尺",true,"2021\u002F2020版教材P69页 顶进过程中，每一顶程要观测并记录各观测点左、右偏差值，高程偏差值和顶程及总j进尺。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]