[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125144,792,1,"单选题","当新辟道路必须从铁路、道路路基下通过时，对原有路线采取必要的加固措施后，可采取( )施工通道管涵。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","顶进法",true,{"key":16,"text":17,"correct":18},"B","顶入法",false,{"key":20,"text":21,"correct":18},"C","支撑法",{"key":23,"text":24,"correct":18},"D","承插法","2021\u002F2020版教材P68页 箱涵顶进施工技术的内容当新建道路必须穿越铁路、道路路基下通过时，通常采用箱涵顶进施工技术。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]