[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1125138,792,1,"单选题","为确定悬臂浇筑段前段标高，施工过程中应加强监测，但监测项目不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","挂篮前端的垂直变形值",false,{"key":16,"text":17,"correct":14},"B","预拱度",{"key":19,"text":20,"correct":14},"C","施工中已浇段的实际标高",{"key":22,"text":23,"correct":24},"D","温度影响",true,"2021\u002F2020版教材P66页 确定悬臂浇筑段前段高程时，应考虑：1）挂篮前端的垂直变形。2）预拱度设置。3）施工中已浇筑段的实际高程。4）温度影响等。因此，施工过程中的监测项目为前三项；必要时结构物的变形值、应力也应进行监测，保证结构的强度和稳定。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]