[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125136":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125136,792,1,"单选题","关于悬臂浇筑混凝土连续梁合龙的说法，错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合龙顺序一般是先边跨，后次跨，再中跨",false,{"key":16,"text":17,"correct":14},"B","合龙段长度宜为2m",{"key":19,"text":20,"correct":21},"C","合龙宜在一天中气温最高时进行",true,{"key":23,"text":24,"correct":14},"D","合龙段混凝土强度宜提高一级","2021\u002F2020版教材P66 预应力混凝土连续梁合龙顺序一般是先边跨、后次跨、再中跨。连续梁（T构）的合龙、体系转换和支座反力调整应符合下列规定：(1)合龙段的长度宜为2m；(2)合龙前应观测气温变化与梁端高程及悬臂端间距的关系；(3)合龙前应按设计规定，将两悬臂端合龙口予以临时连接，并将合龙跨一侧墩的临时锚固放松或改成活动支座；(4)合龙前，在两端悬臂预加压重，并于浇筑混凝土过程中逐步撤除，以使悬臂端挠度保持稳定；(5)合龙宜在一天中气温最低时进行；(6)合龙段的混凝土强度宜提高一级，以尽早施加预应力；(7)连续梁的梁跨体系转换，应在合龙段及全部纵向连续预应力筋张拉、压浆完成，并解除各墩临时固结后进行；(8)梁跨体系转换时，支座反力的调整应以高程控制为主，反力作为校核。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]