[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125135,792,1,"单选题","现浇预应力混凝土连续梁采用悬臂浇筑施工，合龙顺序一般是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","先中跨、后次跨、再边跨",false,{"key":16,"text":17,"correct":14},"B","先次跨、后边跨、再中跨",{"key":19,"text":20,"correct":21},"C","先边跨、后次跨、再中跨",true,{"key":23,"text":24,"correct":14},"D","先边跨、后中跨、再次跨","2021\u002F2020版教材P66 预应力混凝土连续梁采用悬臂浇筑施工合龙顺序一般是先边跨、后次跨、再中跨。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]