[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125119,792,1,"单选题","预应力悬臂盖梁混凝土浇筑和底模拆除要求，说法正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","混凝土浇筑从固定端开始；孔道压浆强度达到设计强度后，拆除底模板",false,{"key":16,"text":17,"correct":14},"B","混凝土浇筑从固定端开始；孔道压浆强度达到设计强度80%后，拆除底模板",{"key":19,"text":20,"correct":21},"C","混凝土浇筑从悬臂端开始；孔道压浆强度达到设计强度后，拆除底模板",true,{"key":23,"text":24,"correct":14},"D","混凝土浇筑从悬臂端开始；孔道压浆强度达到设计强度80%后，拆除底模板","2021\u002F2020版教材P61页 在城镇交通繁华路段盖梁施工宜采用整体组装模板、快装组合支架，从而减少占路时间。盖梁为悬臂梁时，混凝土浇筑应从悬臂端开始；预应力混凝土盖梁拆除底模时间应符合设计要求，如设计无要求，孔道压浆强度应达到设计强度后，方可拆除底模板。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]