[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125104":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1125104,792,1,"单选题","关于承台施工要求，说法正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承台施工前应检查基桩位置，确认符合设计要求",true,{"key":16,"text":17,"correct":18},"B","承台基坑无水，设计无要求，基底可铺10cm厚碎石垫层",false,{"key":20,"text":21,"correct":18},"C","承台基坑有渗水，设计无要求，基底应浇筑10cm厚混凝土垫层",{"key":23,"text":24,"correct":18},"D","水中高桩承台采用套箱法施工时，套箱顶面高程可等于施工期间的最高水位","2021\u002F2020版教材P60页 承台施工前应检查基桩位置，确认符合设计要求。在基坑无水情况下浇筑钢筋混凝土承台，如设计无要求，基底应浇筑10cm厚混凝土垫层。水中高桩承台采用套箱法施工时，套箱应架设在可靠的支承上，并具有足够的强度、刚度和稳定性。套箱顶面高程应高于施工期间的最高水位。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]