[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125092":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1125092,792,1,"单选题","钢板桩围堰施打顺序按施工组织设计规定进行，一般( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由下游分两头向上游施打至合龙",false,{"key":16,"text":17,"correct":14},"B","由上游开始逆时针施打至合龙",{"key":19,"text":20,"correct":21},"C","由上游向下游合龙",true,{"key":23,"text":24,"correct":14},"D","由上游开始顺时针施打至合龙","2021\u002F2020版教材P55页 钢板桩围堰施打顺序：一般从上游向下游合龙。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]