[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125075":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125075,792,1,"单选题","预应力筋张拉后，应及时进行孔道压浆。孔道压浆宜采用( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","石灰浆液",false,{"key":16,"text":17,"correct":18},"B","水泥浆",true,{"key":20,"text":21,"correct":14},"C","水泥砂浆",{"key":23,"text":24,"correct":14},"D","水玻璃浆","2021\u002F2020版教材P47 预应力筋张拉后，应及时进行孔道压浆，多跨连续有连接器的预应力筋孔道，应张拉完一段灌注一段；孔道压浆宜采用水泥浆，水泥浆的强度应符合设计要求，设计无要求时不得低于30MP。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]