[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125071":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125071,792,1,"单选题","关于预应力施工的说法，错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预应力筋实际伸长值与理论伸长值之差应控制在±6%以内",false,{"key":16,"text":17,"correct":18},"B","后张法张拉台座应具有足够的强度和刚度，抗滑移安全系数不得小于1.6",true,{"key":20,"text":21,"correct":14},"C","后张法曲线孔道的波峰部位应留排气孔",{"key":23,"text":24,"correct":14},"D","曲线预应力筋宜在两端张拉","2021\u002F2020版教材P45~46 设计无要求时，实际伸长值和理论伸长值差应控制在6%以内；A正确； 曲线孔道的波峰部位应留提成气孔。C正确； 曲线预应力筋或长度大于等于25m的直线预应力筋，宜在两端张拉；长度小于25m的直线预应力筋，可在一端张拉。D正确。 后张法张拉台座应具有足够的强度和刚度，抗滑移安全系数不得小于1.3，B错误。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]