[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125050":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125050,792,1,"单选题","混凝土配合比设计步骤是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初步配合比设计→基准配合比设计→试验室配合比设计→施工配合比设计",false,{"key":16,"text":17,"correct":18},"B","初步配合比设计→试验室配合比设计→基准配合比设计→施工配合比设计",true,{"key":20,"text":21,"correct":14},"C","试验室配合比设计→基准配合比设计→初步配合比设计→施工配合比设计",{"key":23,"text":24,"correct":14},"D","试验室配合比设计→初步配合比设计→基准配合比设计→施工配合比设计","2021\u002F2020版教材P40页 混凝土配合比设计步骤：（1）初步配合比设计阶段，根据配制强度和设计强度相互间关系，用水灰比计算方法，水量、砂率查表方法以及砂石材料计算方法等确定计算初步配合比（2）试验室配合比设计阶段，根据施工条件的差异和变化，材料质量的可能波动调整配合比（3）基准配合比设计阶段，根据强度验证原理和密度修正方法，确定每立方米混凝土的材料用量（4）施工配合比设计阶段，根据实测砂石含水率进行配合比调整，提出施工配合比",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]