[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1125007":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1125007,792,1,"单选题","以下说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拆除梁或悬挑构件时，应采取有效的下落控制措施，方可切断两端的支撑",false,{"key":16,"text":17,"correct":18},"B","人工拆除挡土墙时，可采用掏掘或推倒的方法",true,{"key":20,"text":21,"correct":14},"C","人工拆除施工应从上至下、逐层拆除、分段进行，不得垂直交叉作业",{"key":23,"text":24,"correct":14},"D","拆除管道及容器时，必须在查清残留物的性质，并采取相应措施确保安全后，方可进行拆除施工","人工拆除挡土墙时，严禁采用掏掘或推倒的方法。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]