[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124998":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1124998,792,1,"单选题","下列关于模板支架、脚手架的搭设和拆除说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工中不得超载，不得在支架上集中堆放物料",false,{"key":16,"text":17,"correct":14},"B","模板支架.脚手架拆除采用机械作业时应由专人指挥",{"key":19,"text":20,"correct":14},"C","脚手架应按规定采用连接件与构筑物相连接，使用期间不得拆除",{"key":22,"text":23,"correct":24},"D","模板支架.脚手架拆除应按施工方案或专项方案要求由下而上逐层进行",true,"本题考查的是模板支架和拱架施工安全措施。模板支架、脚手架拆除应按施工方案或专项方案要求由上而下逐层进行，严禁上下同时作业。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]