[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124988":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124988,792,1,"单选题","混凝土桩堆放时码放层数不宜超过（ ）层。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","5","本题考查的是桩基施工安全措施。混凝土桩支点应与吊点在一条竖直线上，堆放时应上下对准，堆放层数不宜超过4层。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]