[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124972":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124972,792,1,"单选题","地铁车站主体工程后浇带做法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","后浇带位置应设于受力和变形较大处",false,{"key":16,"text":17,"correct":14},"B","后浇混凝土施工应在其两侧混凝土龄期达到28d后进行",{"key":19,"text":20,"correct":21},"C","后浇缝应采用补偿收缩混凝土灌注，并不得低于两侧混凝土强度",true,{"key":23,"text":24,"correct":14},"D","后浇带间距宜为100m","后浇缝施工应符合下列规定：1）位置应设于受力和变形较小处；2）后浇混凝土施工应在其两侧混凝土龄期达到42d后进行；3）后浇缝应采用补偿收缩混凝土灌注，其配合比经试验确定，并不得低于两侧混凝土强度；4）后浇带间距宜为30～60m。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]