[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1124967,792,1,"单选题","城镇管道工程焊接质量检验次序为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对口质量检验→表面质量检验→强度和严密性试验→无损探伤检验",false,{"key":16,"text":17,"correct":14},"B","表面质量检验→对口质量检验→无损探伤检验→强度和严密性试验",{"key":19,"text":20,"correct":14},"C","表面质量检验→对口质量检验→强度和严密性试验→无损探伤检验",{"key":22,"text":23,"correct":24},"D","对口质量检验→表面质量检验→无损探伤检验→强度和严密性试验",true,"焊接质量检验次序：（1）对口质量检验；（2）表面质量检验；（3）无损探伤检验；（4）强度和严密性试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]