[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124959":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124959,792,1,"单选题","当白天气温高于（ ）时，压浆宜在夜间进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30℃",false,{"key":16,"text":17,"correct":14},"B","45℃",{"key":19,"text":20,"correct":21},"C","35℃",true,{"key":23,"text":24,"correct":14},"D","40℃","本题考查的是预应力张拉施工质量事故预防措施。压浆过程中及压浆后48h内，结构混凝土的温度不得低于5℃。当白天气温高于35℃时，压浆宜在夜间进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]