[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124948":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124948,792,1,"单选题","单位工程、分部工程和分项工程开工前，应由（ ）对承担施工的负责人或分包方全体人员进行书面技术交底。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目负责人",false,{"key":16,"text":17,"correct":14},"B","项目生产负责人",{"key":19,"text":20,"correct":21},"C","项目技术负责人",true,{"key":23,"text":24,"correct":14},"D","项目质量负责人","单位工程、分部工程和分项工程开工前，项目技术负责人对承担施工的负责人或分包方全体人员进行书面技术交底。技术交底资料应办理签字手续并归档。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]