[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124942,792,1,"单选题","项目进度控制总目标可按承包的专业或（ ）分解为完工分目标。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","完成阶段",false,{"key":16,"text":17,"correct":14},"B","合同阶段",{"key":19,"text":20,"correct":21},"C","施工阶段",true,{"key":23,"text":24,"correct":14},"D","检验阶段","本题考查的是施工进度调控措施。按承包的专业或施工阶段分解为阶段分目标，重大市政公用工程可按专业工程分解进度目标分别进行控制；也可按施工阶段划分确定控制目标。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]