[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124941,792,1,"单选题","施工进度总目标以（ ）为最终目标。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","缩短工期",false,{"key":16,"text":17,"correct":14},"B","保证质量",{"key":19,"text":20,"correct":21},"C","实现施工合同约定的竣工日期",true,{"key":23,"text":24,"correct":14},"D","节约成本","本题考查的是施工进度调控措施。总目标对工程项目的施工进度加以控制，以实现施工合同约定的竣工日期为最终目标，总目标应按需要进行分解。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]