[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124937":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124937,792,1,"单选题","某市政工程网络计划图如下（单位为月），该工程的关键路线是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→⑤→⑥",false,{"key":16,"text":17,"correct":18},"B","①→②→③→④→⑤→⑥",true,{"key":20,"text":21,"correct":14},"C","①→③→④→⑥",{"key":23,"text":24,"correct":14},"D","①→③→④→⑤→⑥","工期最长的线路为关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]