[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124930":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124930,792,1,"单选题","夜间施工的时间段具体是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","22时～次日4时",false,{"key":16,"text":17,"correct":18},"B","22时～次日6时",true,{"key":20,"text":21,"correct":14},"C","24时～次日4时",{"key":23,"text":24,"correct":14},"D","24时～次日6时","本题考查的是环境保护和文明施工。对因生产工艺要求或其他特殊需要，确需在22时至次日6时期间进行强噪声工作，施工前建设单位和施工单位应到有关部门提出申请，经批准后方可进行夜间施工，并公告附件居民。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]