[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124916":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1124916,792,1,"单选题","施工成本管理措施中的两算对比指的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工图预算与施工预算的对比",true,{"key":16,"text":17,"correct":18},"B","设计概算与施工预算的对比",false,{"key":20,"text":21,"correct":18},"C","设计概算与施工图预算的对比",{"key":23,"text":24,"correct":18},"D","设计概算与估算指标的对比","本题考查的是施工成本管理。两算对比：即施工图预算和施工预算。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]