[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124909":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1124909,792,1,"单选题","延期发出图纸产生的索赔一般为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期索赔",true,{"key":16,"text":17,"correct":18},"B","费用索赔",false,{"key":20,"text":21,"correct":18},"C","人员索赔",{"key":23,"text":24,"correct":18},"D","机械索赔","接到中标通知书后28d内，未收到监理工程师送达的图纸及其相关资料，作为承包方应依据合同提出索赔申请，由于是施工前准备阶段，该类项目一般只进行工期索赔。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]