[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124906":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124906,792,1,"单选题","非承包方原因导致项目拖延和成本增加的，其需在（ ）内向监理工程师以正式函件提出索赔要求。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14d",false,{"key":16,"text":17,"correct":14},"B","21d",{"key":19,"text":20,"correct":21},"C","28d",true,{"key":23,"text":24,"correct":14},"D","15d","本题考查的是施工合同索赔。合同实施过程中，凡不属于承包方责任导致项目拖延和成本增加事件发生后的28d内，必须以正式函件通知监理工程师，声明对此事件要求索赔，同时仍需遵照监理工程师的指令继续施工，逾期提出时，监理工程师有权拒绝承包方的索赔要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]