[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124866":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1124866,792,1,"单选题","竣工测量时，受条件制约无法补设测量控制网，可考虑以施工（ ）的测量控制网点为依据进行测量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有效",true,{"key":16,"text":17,"correct":18},"B","原设计",false,{"key":20,"text":21,"correct":18},"C","恢复",{"key":23,"text":24,"correct":18},"D","加密","竣工测量应按规范规定补设控制网。受条件制约无法补设测量控制网时，可考虑以施工有效的测量控制网点为依据进行测量。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]