[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124816":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124816,792,1,"单选题","二灰混合料基层摊铺施工应在第一次重冰冻到来之前（ ）完成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.5～1.0个月",false,{"key":16,"text":17,"correct":18},"B","1.0～1.5个月",true,{"key":20,"text":21,"correct":14},"C","1.5～2.0个月",{"key":23,"text":24,"correct":14},"D","2.0～2.5个月","本题考查的是石灰工业废渣稳定砂砾基层。摊铺应在春末和夏季组织施工，施工期的日最低气温应在5℃以上，并应在第一次重冰冻到来之前1～1.5个月完成。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]