[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124794":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1124794,792,1,"单选题","高温施工时，混凝土拌合物的初凝时间不得小于（ ）h，低温施工时，终凝时间不得大于（ ）h。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3，10",true,{"key":16,"text":17,"correct":18},"B","2，10",false,{"key":20,"text":21,"correct":18},"C","3，12",{"key":23,"text":24,"correct":18},"D","2，12","本题考查的是混凝土配合比设计、搅拌和运输。高温施工时，混凝土拌合物的初凝时间不得小于3h，低温施工时，终凝时间不得大于10h。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]