[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124790":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124790,792,1,"单选题","改性沥青混合料初压开始温度不低于（ ），碾压终了温度应不低于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","150℃，80℃",false,{"key":16,"text":17,"correct":18},"B","150℃，90℃",true,{"key":20,"text":21,"correct":14},"C","180℃，80℃",{"key":23,"text":24,"correct":14},"D","180℃，90℃","本题考查的是改性沥青混合料面层施工、开放交通及其他。改性沥青混合料除执行普通沥青混合料的压实成型要求外，还应做到：初压开始温度不低于150℃，碾压终了的表面温度应不低于90℃。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]