[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124775":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124775,792,1,"单选题","挖方路基施工做法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","路基施工前，应将现况地面上积水排除、疏干",false,{"key":16,"text":17,"correct":14},"B","挖土时应自上向下分层开挖",{"key":19,"text":20,"correct":21},"C","在距直埋缆线1m范围内必须采用人工开挖",true,{"key":23,"text":24,"correct":14},"D","压路机不小于12级","（1）路基施工前，应将现况地面上积水排除、疏干，将树根坑等部位进行技术处理。 （2）挖土时应自上向下分层开挖，严禁掏洞开挖。机械开挖作业时，必须避开构筑物、管线，在距管道1m范围内应采用人工开挖；在距直埋缆线2m范围内必须采用人工开挖。 （3）压路机不小于12级。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]