[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124706":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124706,792,1,"单选题","支、吊架安装的规定表述中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支架结构接触面应洁净.平整",false,{"key":16,"text":17,"correct":18},"B","临时性的支.吊架应做出明显标记，并应在管道安装过程中进行拆除",true,{"key":20,"text":21,"correct":14},"C","支.吊架的焊接，焊缝不得有漏焊.缺焊.咬边或裂纹等缺陷",{"key":23,"text":24,"correct":14},"D","管道支架支承面的标高可采用加设金属垫板的方式进行调整","本题考查的是供热管网附件及安装。选项B的正确说法“当使用临时性的支、吊架时，应避开正式支、吊架的位置，且不得影响正式支、吊架的安装。临时性的支、吊架应做明显标记，并应在管道安装完毕后拆除”。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]