[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124691,792,1,"单选题","对接热力管道管口时，应检查管道平直度，在所对接管子的全长范围内，最大偏差值应不超过（ ）mm。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":18},"B","10",true,{"key":20,"text":21,"correct":14},"C","15",{"key":23,"text":24,"correct":14},"D","20","本题考查的是供热管道安装与焊接。对接管口时，应在距接口两端各200mm处检查管道平直度，允许偏差为0～1mm，在所对接管道的全长范围内，最大偏差值不应超过10mm。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]