[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124653,792,1,"单选题","球墨铸铁管（有水泥砂浆衬里）、钢管（有水泥砂浆衬里）、化学建材管浸泡（ ）h后，才进行水压试验。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":18},"B","24",true,{"key":20,"text":21,"correct":14},"C","36",{"key":23,"text":24,"correct":14},"D","72","本题考查的是给水排水管道试验方案与准备工作。球墨铸铁管（有水泥砂浆衬里）、钢管（有水泥砂浆衬里）、化学建材管不少于24h；内径大于1000mm的现将钢筋混凝土管渠、预（自）应力混凝土管、预应力钢筒混凝土管不少于72h；内径小于1000mm的现浇钢筋混凝土管渠、预（自）应力混凝土管、预应力钢筒混凝土管不少于48h。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]