[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124641,792,1,"单选题","构筑物水池满水试验流程为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","试验准备→水池内水位观测→水池注水→蒸发量测定→整理试验结论",false,{"key":16,"text":17,"correct":14},"B","试验准备→水池注水→蒸发量测定→水池内水位观测→整理试验结论",{"key":19,"text":20,"correct":21},"C","试验准备→水池注水→水池内水位观测→蒸发量测定→整理试验结论",true,{"key":23,"text":24,"correct":14},"D","试验准备→蒸发量测定→水池注水→整理试验结论→水池内水位观测","构筑物水池满水试验流程为试验准备→水池注水→水池内水位观测→蒸发量测定→整理试验结论。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]