[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124633":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124633,792,1,"单选题","张拉段无粘结预应力筋长度大于25m而小于50m时，宜采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一端张拉",false,{"key":16,"text":17,"correct":18},"B","两端张拉",true,{"key":20,"text":21,"correct":14},"C","分段张拉",{"key":23,"text":24,"correct":14},"D","电热张拉","本题考查的是现浇预应力钢筋混凝土水池施工技术。张拉段无粘结预应力筋长度小于25m时，宜采用一端张拉；张拉段无粘结预应力长度大于25m而小于50m时，宜采用两端张拉；张拉段无粘结预应力筋长度大于50m时，宜采用分段张拉和锚固。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]