[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124632":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124632,792,1,"单选题","关于沉井下沉监控测量的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","下沉时标高.轴线位移每班至少测量一次",false,{"key":16,"text":17,"correct":18},"B","封底前自沉速率应大于10mm\u002F8h",true,{"key":20,"text":21,"correct":14},"C","如发生异常情况应加密量测",{"key":23,"text":24,"correct":14},"D","大型沉井应进行结构变形和裂缝观测","本题考查的是沉井的下沉施工。下沉时标高、轴线位移每班至少测量一次，每次下沉稳定后应进行高差和中心位移量的计算；终沉时，每小时测一次，严格控制超沉，沉井封底前自沉速率应小于10mm\u002F8h。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]