[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1124613,792,1,"单选题","水池满水试验必须在规定的条件下进行，以下满水试验前必须具备的条件汇总错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","池体的混凝土或砖.石砌体的砂浆已达到设计强度要求",false,{"key":16,"text":17,"correct":14},"B","现浇钢筋混凝土池体的防水层.防腐层施工之前",{"key":19,"text":20,"correct":14},"C","装配式预应力混凝土池体施加预应力且锚固端封锚以后，保护层喷涂之前",{"key":22,"text":23,"correct":24},"D","砖砌池体防水层施工以后，石砌池体勾缝以前",true,"本题考查的是构筑物满水试验必备条件与准备工作。水池满水试验应在现浇钢筋混凝土池体的防水层、防腐层施工之前；装配式预应力混凝土池体施加预应力且锚固端封锚以后，保护层喷涂之前；砖砌池体防水层施工以后，石砌池体勾缝以后。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]