[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1124585,792,1,"单选题","喷锚加固时，喷射混凝土施工前，应做混凝土凝结时间试验，初凝和终凝时间不应大于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3min和5min",false,{"key":16,"text":17,"correct":14},"B","3min和10min",{"key":19,"text":20,"correct":21},"C","5min和10min",true,{"key":23,"text":24,"correct":14},"D","5min和15min","喷射混凝土使用前应做凝结时间试验，要求初凝时间不应大于5min，终凝不应大于10min。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]