[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124549":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1124549,792,1,"单选题","下列隧道施工方法中，当隧道穿过河底时不影响施工的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","新奥法",false,{"key":16,"text":17,"correct":14},"B","明挖法",{"key":19,"text":20,"correct":14},"C","浅埋暗挖法",{"key":22,"text":23,"correct":24},"D","盾构法",true,"在松软含水地层、地面构筑物不允许拆迁，施工条件困难地段，采用盾构法施工隧道能显示其优越性：振动小、噪声低、施工速度快、安全可靠，对沿线居民生活、地下和地面构筑物及建筑物影响小等。采用盾构法施工，当隧道穿过河底或其他建筑物时，不影响施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]