[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124532":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1124532,792,1,"单选题","现浇预应力钢筋混凝土连续梁施工时，支架和模板完成后应进行预压，其作用是消除基础的沉陷和（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支架弹性变形",false,{"key":16,"text":17,"correct":18},"B","支架非弹性变形",true,{"key":20,"text":21,"correct":14},"C","混凝土收缩及温度变形",{"key":23,"text":24,"correct":14},"D","混凝土连续梁预拱度","本题考查的是支（模）架法。现浇预应力混凝土连续梁施工中，各种支架和模板安装后，宜采取预压方法消除拼装间隙和地基沉降等非弹性变形。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]