[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1124531":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1124531,792,1,"单选题","在移动模架，上浇筑预应力混凝土连续梁时，浇筑分段工作缝必须设在（ ）附近。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","弯矩零点",true,{"key":16,"text":17,"correct":18},"B","1\u002F4最大弯矩点",false,{"key":20,"text":21,"correct":18},"C","1\u002F2最大弯矩点",{"key":23,"text":24,"correct":18},"D","弯矩最大点","现浇预应力混凝土连续梁的常用施工方法有支架法、移动模架法和悬臂浇筑法。在移动模架法上应注意：支架长度必须满足施工要求。支架应利用专用设备组拼，在施工时能确保质量和安全。浇筑分段工作缝，必须设在弯矩零点附近。箱梁外，内模板在滑动就位时，模板平面尺寸、高程、预拱度的误差必须在容许范围内。混凝土内预应力筋管道、钢筋、预埋件设置应符合规范和设计要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]